PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer C. You are not a magician to prevent all issues from occurring.
There is no way someone can prevent all issues from occurring, and that is not the purpose of risk management anyway. The purpose is to minimize threats, optimize opportunities, support the organization in achieving its objectives and support stakeholders to take informed decisions. For these purposes, budget is allocated to risk management. In case stakeholders are unable to see the added value Risk Management is brining to the organization, then one of the cause can probably be poor communications.
C is the correct answer