PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The competitor's delay is an external opportunity that the project team can exploit to add features and improve market position. A vendor going out of business is a threat (even if a silver lining emerges), a denied permit is a realized threat leading to cancellation, and finding a bug is quality control, not opportunity capture. Opportunities are uncertain positive events that can be exploited.