PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Lessons learned from similar projects are a valuable input for identifying risks (they show what has gone wrong before), but they are not themselves a threat. Incomplete requirements, resource constraints, and scope creep are all common sources of project threats. Lessons learned are part of organizational process assets that help with risk identification.