PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The project sponsor is responsible for providing resources and funding for the project, including risk responses. The risk owner is responsible for monitoring specific risks and implementing agreed-upon responses. A risk manager (if designated) coordinates risk activities, and team members may execute specific response actions. However, securing funding and resources is a sponsor responsibility.