PMI Risk Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The primary output of Perform Qualitative Risk Analysis is updates to the risk register, including relative risk rankings or priority lists for the project risks. This prioritization helps the project team focus on the most critical risks. Risk response strategies are developed in the Plan Risk Responses process, while quantitative analysis results and specific contingency reserve amounts come from Perform Quantitative Risk Analysis.