PMI Professional in Business Analysis · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
You need to update the changes first and then review it with concerned stakeholders. So its A.
A is correct answer. First is to record and then do impact analysis. The base line can only be changed via following Change control process not with only discussions with SHs.
To track requirements throughout the lifecycle of a project and ensure the delivery of the expected solution, a business analyst should follow a requirements management process