PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
A and B are similar stories, and not "same" stories. So although A & C are already completed, reviewing what went wrong during estimation(retrospective), and re-estimating all the stories would be the right approach.
A. Increased points for B: This assumes the error applies only to story A and B will be similar, which might not be true. Overestimation can lead to under-delivering in other areas. B. Add points to current iteration: This doesn't address the underlying reason for the discrepancy and doesn't improve future estimations. C. Assign more resources: Throwing resources at a potentially inaccurate estimate is inefficient and doesn't guarantee faster completion.
Option D Estimate Activity Durations: This process emphasizes the need to update estimates throughout the project based on actual performance data and align with continuous improvement.