PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Agile acknowledges uncertainty, especially in rapidly changing markets, while still providing stakeholders with needed information. A vision with near-term detail and transparency about uncertainty beyond the horizon balances stakeholder communication with reality. Refusing dates entirely (C) is unhelpful, while false precision (A, D) creates unrealistic expectations and commitment stress.