PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D 60% A 40%
In Agile, scrum master is the servant leader who is responsible to resolve impediment. Therefore, if that colleague's absence caused an issue. We should notify scrum master not product owner. therefore, A is not correct. In Agile, team member is generalized specialist. A high performance team can work collaborate and help each other. One person's absence should not be a big issue so not caused any problem. The team can reach the iterative goal and notify PO. therefore, the answer should be D
What should the 'team' do? D. is the clear answer, the Team takes on the responsibilities and PO gets notified. In Agile, one aims to have cross-functional Teams, where the Team members can absorb any work planned work.