PMI Agile Certified Practitioner · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The second principle of the Agile Manifesto states: "Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage." A rigid change control process contradicts agile values. Instead, agile teams should build processes that accommodate change through short iterations and continuous stakeholder collaboration.