CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Negotiate with functional managers ✅ Here's why: In a matrix organizational structure, team members typically report to functional managers, who control their time and assignments. If team members don’t have enough time for project work, the project manager needs to negotiate with the functional managers to: Adjust priorities, Allocate more dedicated time to project tasks, Balance workload between functional and project work.
Its a matrix org, meaning that team members are going to be reporting to the PM and the FM (No not the radio waves) Rather than just one or the other. If theyre too busy working on things for the functional manager then the PM is probably going to have to secure more time for the Project mentioned in the question
I’m going C In a matrix organizational structure, team members often report to both a functional manager and a project manager. If team members don't have enough time to dedicate to project activities, the project manager should negotiate with the functional managers to secure more of the team members' time for the project. This can involve discussing the project's priorities, deadlines, and resource needs.