Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Precedence Diagramming Method (PDM) ✅ Here's why: During the project initiation or planning phase, when a project manager (PM) needs to: Construct a project schedule Show project dependencies between tasks (e.g., what comes before/after) The Precedence Diagramming Method (PDM) is the best tool for this task.
The most commonly used network diagramming method is the precedence diagramming method (PDM) . PDM uses boxes to represent the project milestones and arrows that represent activities. They also show the dependencies between the tasks. Heldman, Kim. CompTIA Project+ Study Guide : Exam PK0-005, John Wiley & Sons, Incorporated, 2022. ProQuest Ebook Central,
No definitely not C, it is Definitely D. CPM highlights the dependencies and the longest duration bc of the critical tasks that need to be created.