The correct answer is: ✅ C. Milestones (Most Voted and Correct) Here's why: Milestones are activities or events with zero duration that mark significant points or achievements in the project schedule. They represent key deliverables, decision points, or phase completions but don’t require time to complete.
C - Activities with zero duration are called "milestones." Milestones represent significant points in a project's timeline that mark the completion of a specific phase, task, or deliverable. They do not require any time to complete since they are essentially events that indicate the achievement of a certain goal.
milestones as zero-duration tasks