CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The best answer is: ✅ C. RACI (Most Voted and Correct) Here's why: A RACI matrix clearly defines the roles and responsibilities of team members on tasks or deliverables. It shows who is Responsible, Accountable, Consulted, and Informed for each activity, which helps clarify how different roles interact and collaborate. This promotes clear communication and avoids confusion over responsibilities.
Both RACI and PERT seem right at first but a PERT describes tasks and work while a RACI describes the roles people play. RACI is the best answer because it provides a framework for how poeple on a project would interact with each other.