CompTIA Project+ · CompTIA
Select 2 answers.
This question asks for 2 answers, but our data marks only 1. Compare with the community discussion below for the full answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The two documents that should be used to record the unexpected event and the workaround are: ✅ D. Issue log (Most Voted) ✅ E. Change log (Most Voted) Explanation: Issue Log: This is the primary document to record unexpected events, problems, or obstacles that arise during the project. The workaround, as a temporary solution to the issue, should also be documented here. Change Log: Since implementing a workaround often involves a deviation from the original plan or baseline, this change (even if temporary) should be recorded in the change log for tracking all project changes.
Issue Log & Change Log. Defect Log is the same as an Issue Log (and I can't find any reference to this in my Sybex book.) Issue log because its an issue. Change log because they did essentially an emergency change.
Agree with DE