CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: ✅ B. A project manager did not release the resources. (Most Voted and Most Accurate) Here's why: If employees are showing 200% allocation, it means they appear to be working on more than one project at the same time, or their time is being double-counted. This typically happens when: A previous project still lists them as active resources, even though they have moved to a new one. The project manager failed to update the system to officially release those resources from the old project
The allocation refers to being assigned to a project. One PM didn't release them from their project, while the 2nd PM assigned them to their project.