CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Note that the yellow bar is BELOW the red bar - they aren't atop it. They aren't exceeding it. This means they are BEHIND schedule. The bar towards the bottom is the planned cost. The yellow bar is our actual cost... which is ABOVE the planned costs. Meaning we are OVER budget. Combining these two things, we are BEHIND schedule and OVER budget.
Behind schedule over budget
yea, there are great youtube videos explaining burnup charts for anyone that needs further explanation