CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: C. Task board ✅ Explanation: A task board (often used in Agile or Scrum) visually tracks the progress of tasks during daily stand-up meetings. It typically shows columns like To Do, In Progress, and Done to help the team quickly see status and bottlenecks.
Task Board is the answer. A dashboard is a real-time view of the status of the project generally displayed visually for executives. Whiteboard is for collaborative meetings. Decision board is not something I'm familiar with for the Project+.