CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
It is D. The key to this question is the stage it is happening. It happens during the planning phase in which you escalate to the main stakeholders. Once the baselines are set, then the CCB would be responsible for any changes.
The correct answer is: D. Have a meeting with the project sponsor and main stakeholders ✅ Explanation: The project manager has identified unaddressed legal requirements that could lead to serious financial penalties — a critical issue that affects project feasibility, scope, and organizational compliance.
First thing to do is submit to CCB