Project charter is first. It is the first document produced after PM is assigned
The correct answer is: C. Project charter ✅ Explanation: The project manager is concerned about stakeholder expectations and wants to clearly communicate the boundaries of the project — in other words, what the project will and will not do. The first document to address this at a high level is the Project Charter, because: It formally authorizes the project. It outlines the objectives, high-level scope, boundaries, and key deliverables. It helps align stakeholders early on and sets clear expectations. It’s typically the first formal document created once the project begins — especially important since the PM was not part of the initial negotiations.
The project charter should be produced first. The project charter is a high-level document that describes the project, its goals, and its stakeholders. It is used to get the project started and to obtain approval from senior management. The detailed scope statement is a more detailed document that describes the project's deliverables, scope, and schedule. It is used to communicate the project to stakeholders and to ensure that everyone is on the same page.