CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Issue log ✅ Explanation: A hurricane delaying critical equipment is an unexpected event that affects project progress. This type of event is best recorded in an issue log, which is specifically designed to track and manage problems that arise during project execution
Issue Log as it is used not only for software bugs, it is also used to track general bugs (staffing, schedule, and vendor delays)
A change control log is used to track any changes made to a project, including unexpected events like a hurricane that significantly impacts the project schedule or deliverables. It documents the reason for the change, the impact of the change, the proposed solution, and the approval process.