CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: D. Planning Explanation: Identifying the baseline go-live date, operational training, and handoff procedures are all activities that happen during the planning phase of a project. Planning involves defining timelines, training plans, and transition strategies before actual execution.
Question is designed to mislead you. YES - Go-live, operational training, and handoff are all closing activities BUT - one pivotal term is 'identify'. The team is meeting to identify these elements, not execute them. AND - another pivotal term in this question is 'baseline'. When a date is being baselined, it represents a planned timeline.