CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: D. A transition plan Explanation: Let's break down what the team is doing: Defining operational training – Preparing end users and support staff to take over operations. Discussing a go-live date – Setting the point at which the system or process becomes operational. Describing the operational handoff – Planning how the responsibilities will transfer from the project team to the operational team. These are all key components of a transition plan, which ensures a smooth move from the project phase into steady-state operations
Per AI source... D. A transition plan. A transition plan outlines the activities and processes required to transition the project deliverables from the project team to the operational or support team. It typically includes details about training, go-live dates, operational handoff procedures, and any other activities necessary to ensure a smooth transition from project implementation to operational use. Developing a transition plan is essential for ensuring that the project's outcomes are effectively integrated into ongoing operations and support activities.