CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Multiauthoring software ✅ Explanation: The question focuses on version control for documentation of requirements — a process that involves tracking changes, maintaining history, and often enabling collaboration among multiple contributors.
The question states that a project manager is being very careful keeping version control of documentation, very different from saying he is the sole person documenting requirements. Key word is version control, therefore going with A.
Multiauthoring software generally has some sort of version control implemented in it.