CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Maintenance window Here's why: After the Change Control Board (CCB) approves a change (in this case, deploying a new networking device), the next logical step is scheduling the implementation — and that typically involves selecting an appropriate maintenance window. A. Maintenance window ✅ Once the change is approved, the project manager must plan when to deploy it — ideally during a time that minimizes disruption. This is known as a maintenance window. It's critical in production environments to ensure availability and reduce risk to operations.
Answer is A: Maintenance Window, would be scheduled to ensure minimal downtime to implement the change since it does not state time is critical for this change to occur. Both a Risk Assessment and Operational Security Assessment would have been conducted prior to going to the CCB for consideration. While a Validation check is done after the change is implemented to ensure its function.