In the Q is described condition that DB renewal has not started, not finished so it's B, than in real life more likely can be that DB need to finish before mobile application project will start.
he correct answer is: ✅ B. Start-to-start Here's why: A Start-to-Start (SS) relationship means that one task cannot start until another task has started. In this case: The mobile application project cannot start until the database renewal project has started. So, the start of the mobile app project depends on the start of the database renewal project.
You would want the database renewal to be finished. What if its a completly different database when that project is finished? If you based your mobile app on the older database...