CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: ✅ C. Create a record in the issue log Here's why: When a team member discovers a malfunctioning procedure (i.e., a problem or defect), the first step is to document it as an issue in the issue log. This: Ensures the problem is formally recorded and tracked Allows the project team to prioritize, assign, and manage the resolution Provides visibility and accountability The issue log is the primary tool for managing problems that arise during a project.
C - When a team member discovers a malfunctioning procedure in the system, the first step should be to create a record in the issue log. This allows the issue to be formally documented, ensuring that it is tracked and managed appropriately. Once the issue is recorded, the project team can proceed with analyzing the problem, detailing a proposed solution, and taking appropriate actions. Updating the risk register, documenting the finding in the change log, and detailing a proposed solution can all follow after the initial issue is recorded in the issue log.