CompTIA Project+ · CompTIA
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: ✅ B. Preliminary scope statement Here's why: Once the project objectives and success criteria are documented in the project charter, the next logical step is to define the preliminary scope statement. This outlines: What the project will and will not include High-level deliverables Major boundaries and constraints The preliminary scope gives stakeholders and the project team a clear picture of what the project is aiming to deliver — it builds upon the objectives and lays the groundwork for more detailed planning.
i think B
B - After documenting the project objectives and success criteria, the next step in completing the project charter is to define the preliminary scope statement. This statement outlines the high-level boundaries and deliverables of the project, helping to provide a clear understanding of what the project will and will not involve. Once the scope is defined, other aspects like proposed solution design, responsibility assignment matrix, and initial budget baseline can be developed in alignment with the project's scope and objectives.