Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Crashing: moderate risk increase. Fast Tracking: higher risk.
I believe is fast tracking , because crashing means adding resources which increases the risk and costs
Crashing increases resources to the Project and Fast tracking of the project increases risk to the project