Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Explanation: • BAC = 1,550,000 • AC = 725,000 • EV = (BAC * 0.45) = (1,550,000 * 0.45) = 697,500 • PV = planned % * BAC = 0.50 * 1,550,000 = 775,000 • CPI = EV / AC = 697,500 / 725,000 = 0.96 • SPI = EV / PV = 697,500 / 775,000 = 0.90
The answer is obvious from the options. SPI of 0.9 is worse than CPI of 0.96