Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The program manager should evaluate which component's need has higher priority based on its criticality to the program schedule, benefits realization, and overall program objectives. An informed allocation decision considers the impact on the entire program, not just individual components. Exam tip: Resource conflicts between components are resolved at the program level based on program priorities and benefits impact.