- The program schedule should be a master schedule showing high-level milestones for each component, key inter-component dependencies, and critical decision points. It provides a program-level view without duplicating the detail in project-level schedules. Exam tip: The program schedule is a coordination tool—it shows milestones and dependencies between components, not task-level details.