Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The most important activity during Program Closure is transitioning program benefits to sustaining operations to ensure they continue to be realized after the program ends. This includes knowledge transfer, operational readiness verification, and establishing benefit sustainability mechanisms. Exam tip: Benefits must outlive the program—closure focuses on ensuring the organization can sustain benefits without the program structure.