- Program Closure is entered when the program has delivered (or transitioned) its intended benefits so remaining sustainment can be handled by operations, or when a decision has been made to terminate the program. Closure may be planned (benefits delivered/transitioned) or unplanned (strategic shift, poor performance, or loss of justification). Exam tip: Budget exhaustion or staff turnover alone does not trigger closure—benefit delivery/transition or a formal terminate decision does.