Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Progressive elaboration in program management means iteratively refining and detailing program plans as more information becomes available. Early plans are high-level and become more detailed as the program progresses, new information emerges, and uncertainties are resolved. Exam tip: Programs embrace uncertainty—progressive elaboration is the mechanism for managing it through iterative planning refinement.