Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- When a new regulatory requirement affects multiple components, the program manager should assess the impact at the program level to ensure a consistent and coordinated response. The program risk register should be updated, and the response should be cascaded to affected components. Exam tip: Cross-cutting issues like regulatory changes must be managed at the program level to ensure consistency and avoid conflicting responses across components.