Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
EAC (Estimate at Completion) forecasts the total cost to complete the program. Subtracting the actual cost (AC) gives the remaining investment needed: EAC - AC. Note: EAC can be calculated in multiple ways (e.g., EAC = AC + (BAC - EV)/CPI), but the requested metric for “how much more will need to be invested” is EAC - AC.
EAC − AC → Remaining cost to complete the work
C. BAC/CPI