A program manager is leading a program introducing a new customer relationship management solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance. A stakeholder from the sales department now requests a new feature to integrate the platform with another application. The program manager advises that this is out of scope and requests additional funding via the formal change management process, and the new scope is approved. What should the program manager do next?
Select one answer.