Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The Program Work Breakdown Structure (PWBS) provides a hierarchical decomposition of the total program scope, showing program components (projects, subsidiary programs, and program-level activities) and their interrelationships. Unlike a project WBS, it does not decompose to the work package or activity level for each project. Exam tip: The PWBS stays at the component level—individual projects create their own detailed WBS.