Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The GHW Project was terminated due to trade-offs and affordability, which is fundamentally a change to the project’s scope within the program. Scope control is the process that manages changes to the project scope and ensures any such changes are properly evaluated and approved
When a project is terminated within a program due to strategic trade-offs and affordability, PMI expects the project to undergo formal closure activities. A financial audit ensures that.
Terminated --> should do final verification to close. Control scope if project is continue, need to control scope to make sure no crepe, no gold plating