Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The stakeholder engagement assessment matrix compares each stakeholder's current engagement level (unaware, resistant, neutral, supportive, leading) with the desired level. Gaps between current and desired states identify where engagement efforts need to be focused. Exam tip: The engagement assessment matrix is a gap analysis tool—it shows where you are versus where you need to be for each stakeholder.