Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Program-level stakeholder management addresses a broader and more diverse range of stakeholders than project-level management. It includes executives, governance boards, regulatory bodies, cross-organizational groups, and community stakeholders whose interests span the entire program. Project-level management focuses more on direct participants. Exam tip: Program stakeholder management is broader and more strategic than project stakeholder management—it deals with higher-level organizational and external stakeholders.