Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
C is correct answer BAC = 1750000, AC = 620000 EV = 0,35 x 1750000 = 612,5 CPI = EV/AC = 612,5/620000 = 0,98175 PV = 0,4 x BAC = 0,4 x 1750000 = 700 SPI = EV/PV = 612,5/700 = 0,875 =0,88