Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- When the operations team is not ready, the program manager should collaborate with them to develop or refine the transition plan, provide additional training or support, and adjust the closure timeline if necessary to ensure successful transition. Forcing a transition creates operational risk. Exam tip: A successful transition requires operational readiness—work with the receiving organization to bridge the gap rather than forcing handoff.