Program Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- When strategic priorities shift, the program manager should first assess how the change impacts the program's strategic alignment and expected benefits. This assessment informs whether the program should be modified, redirected, or closed. Hasty decisions without analysis can lead to poor outcomes. Exam tip: When strategy changes, always assess impact first before taking action—this is a recurring theme on the PgMP exam.