Portfolio Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource conflicts between portfolio components should be escalated to the governance board with clearly defined options and recommendations. The governance board has the authority to make cross-component resource allocation decisions based on strategic priorities. Allowing self-resolution or unilateral actions undermines portfolio governance.