Each year, you update the portfolio roadmap so people within the organization can see component status, interdependencies, constraints, and business value, among other things. This year, however, two major programs in the portfolio were cancelled as they were government contracts, and the government lacked funds to complete them. Your management then had to reduce staffing. These two programs had dependencies with other components in the portfolio. This means that: