After receiving a regular resource utilization report, the portfolio manager has identified two portfolio components that are competing for the same key resource. The unavailability of this resource has the potential to delay both projects. Some stakeholders have complained to the executive sponsor that they were not made aware of the situation. In order to ensure that similar situations are properly addressed in the future, the portfolio manager should update the portfolio:
Select one answer.