ITIL 4 Foundation · ITIL
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
C. A standard change is a type of change that is pre-authorized and routine, with a well-defined process for execution that has a low level of risk and has been approved in advance. It is typically used for changes that are repetitive, low impact, and have been proven to be successful through experience.
For me answer is C, using the elimination process technique A - Normal change "for review" B - Emergency change "critical software patch" C - Standard change "normall this is pre-approved" D - Emergency change "major incident"
I have been working on many CHGs over the years ... 'B' mentined the "critical" so it means an Emergency change -> as soon as possible in case of 'D' I guess a Normal change would be fine -> if you make any change you need a nornal CHG an should be approved on the CAB. in 'A' two phase of the change workflow mentined about the Change Management lifecycle so only 'C' remains, but would notice that application installation allowed only if it's on the "green list" and it's widely used in your organization.