B is correct
5.2.4 Change enablement Normal changes: These are changes that need to be scheduled, assessed, and authorized following a process. Change models based on the type of change determine the roles for assessment and authorization.
5.2.4 Change enablement All changes should be assessed by people who are able to understand the risks and the expected benefits; the changes must then be authorized before they are deployed.